High Voltage Upgrade, Newcastle University
Project Overview
Newcastle University buildings on the HIN site are currently fed from the HV circuits which were setup for the old General Hospital. Vandalism and theft at the old General Hospital site resulted in damage to one of the substations and power outages for the NU buildings.
As a result of this and as part of the wider site masterplan, a new HV connection is required to increase resilience and allow for eventual decommissioning of the NHS HV network on the site.
The new connection will require a new substation, HV equipment, LV equipment and transformers.
Services and Value Added